Generator for a construction site

On a building site, power is usually needed before a permanent grid connection exists. A correctly designed unit keeps plant, facilities and site technology running without unnecessary downtime — and in some projects it later stays as the building's standby source.

  • Trailer and container executions
  • Outputs for plant and facilities
  • Fast deployment

Why construction sites need their own source

On a construction site, power is needed earlier than a permanent electrical connection is available. The generator therefore often serves as a temporary source for site plant, facilities, lighting and other operational parts of the project.

In some projects the unit stays on site after completion and continues as the standby source of the building. We therefore adapt the design of the solution not only to the course of construction but also to the future use of the equipment.

What an outage or missing connection causes on site

Project schedule at risk

Concrete production on site is tied to the construction schedule. A power outage at a critical moment can delay the whole project.

Loss of material

Fresh concrete mix has limited workability. An interruption of production or mixer cooling at the wrong moment can mean the loss of the whole batch.

Plant cannot run

Welding sets, cranes, pumps and mixers need stable power — without it the site stops.

Temporary facilities without power

Site offices, welfare facilities and lighting depend on a temporary source until the connection is commissioned.

Where a generator for a construction site makes sense

No permanent connection

Sites outside the reach of the distribution grid, or where the connection has not yet been commissioned.

Insufficient connection capacity

Sites where the available connection cannot cover the full output of the construction technology — the generator supplements or replaces the grid source.

Moving sites

Equipment that travels from site to site together with the technology.

Infrastructure projects

Roads, railways, tunnels and bridges with long construction periods and heavy plant.

Night work and winter

Lighting, heating and concreting in reduced visibility and low temperatures.

Primary source or backup — it depends on the deployment

Generator as the primary source on site

  • Where no connection exists or its capacity is insufficient.
  • Sized for continuous operation during the working shift and beyond.
  • Larger fuel autonomy and service adapted to intensive duty.

Generator as a supplementary or backup solution

  • Where the connection covers basic operation but not peak loads.
  • Backup for critical site processes — concreting, pumping, cooling.
  • Automatic takeover possible with ATS where it makes sense.

What must be considered in the design

Real load including peaks

Total consumption of the technology including starting peaks of motors. Welding sets, cranes and mixers have high starting currents.

Mobility

The way the unit is transported, its weight, dimensions and the requirements for fast installation at a new location. Container or trailer executions ease the move with standard transport.

Rough site conditions

Terrain conditions, dust, humidity, temperature and requirements for foundation stability. A mobile unit must work reliably in a demanding construction environment.

Noise limits

Distance from inhabited areas or statutory limits on site may require acoustic measures — a canopied unit or container execution.

Fuel autonomy

The required length of continuous operation determines the tank size — from one shift through all-day operation to several days without refuelling.

Emissions on site

In locations with emission requirements or near settlements, a Stage V engine may be appropriate. It depends on the specific conditions of deployment and local regulations.

Service in the field

Access to service support, spare-parts availability and contracted service corresponding to the duty regime and location of deployment.

It is not just a generator — it is a complete functional system

Industrial generator units

Industrial AKSA generators with Perkins, Doosan or Volvo Penta engines. Outputs matched to the requirements of the specific site.

Switchboards and connections

Power and control switchboards, cable interconnections and coordination with the site's electrical installation. Designed as part of the whole solution.

Fuel storage

Integrated or separate tank sized for the required autonomy of operation. Including a drip tray and a connection for mobile refuelling.

Mobile executions

Unit in a mobile container or on a trailer chassis for easy transport and fast commissioning at a new location.

Acoustic execution

Sound-attenuated canopy or container execution for installations with noise requirements. Chosen according to the location and surroundings.

Commissioning and service

Energisation, load tests, documentation handover and service setup. Service arrangements adapted to the duty regime and location of deployment.

Delivery and operation on site

  1. Step 1

    Specify the phase and load

    Tell us the project phase, the required output and how the unit will be used — plant, facilities, lighting or process technology.

  2. Step 2

    Design and quotation

    We propose the output, execution (trailer, container, canopy) and fuel autonomy for the site schedule.

  3. Step 3

    Delivery, placement, connection

    We arrange transport, placement, electrical connection and commissioning on site. We take over the whole coordination.

  4. Step 4

    Operation and relocation

    During the project we handle service and, where needed, relocation of the unit between workplaces.

Related generator power pages

Ratings are indicative, not a full-facility guarantee — the required PRP or ESP rating is confirmed from your load profile, starting loads and critical circuits during project sizing.

Czech projects — scope as agreed

For Czech projects the delivery may include, as agreed: generator supply, design of the installation, commissioning on a prepared site, turnkey realization and a service contract. The scope is always clarified together during consultation and confirmed in the quotation.

International supply — EXW CZ/NL

International direct sales are preferably EXW Czech Republic / Netherlands; transport is agreed individually. Installation and service abroad are possible in agreed cases and are always confirmed individually by location and model. Manufacturer warranty.

We will help you design the generator

We will prepare a suitable solution according to the project phase, required output and the way the equipment will be used on site — without obligation.